2006 Street Maintenance Program Project
CIP#
PE-86070
BARRON PARK MEETING
AGENDA
Time:
Place:
INVITEES: PLEASE
ATTEND
All interested residents of
Matt Raschke Engineer, Public Works 329-2469
Murdo Nicolson Engineering Technician III, Public Works 617-3154
Doug Moran
PURPOSE
OF MEETING:
To inform the
·
Paving
and valley gutter work on
·
A
·
Status
of
To inform the residents of any future and
planned work in
DISCUSSION
ITEMS:
1. INTRODUCTIONS
2. SCHEDULE
A. Approximate
duration and timing for construction.
The Contractor will submit a detail schedule prior to start of
construction. Anticipated construction
starting for Phase II is early summer.
3. HOURS OF WORK
A. Work shall be
allowed to take place between
4. NOTIFICATION TO RESIDENTS
A. The City will
distribute the general notices to the residents on the affected streets
approximately two (2) weeks before the Street Maintenance Program Project
starts.
B.
The
Contractor will distribute advance notices to residents on the streets to be
closed. There will be two separate notices:
seven days in advance of, and 24 hours in advance of closing and/or
resurfacing of each individual street.
C.
You
could also find the information on the City web site
(http://www.city.palo-alto.ca.us/streetmaintenance/notices.html) street
maintenance section after the contract has been awarded by the City Council.
5. TREE
TRIMMING
A. Where the
6.
TRAFFIC
CONTROL
A. The
Contractor will submit a detail traffic control plan prior to beginning
construction.
B. The
Contractor will post the “No Parking” and “Work Description” signs on a
barricade 72 hours prior to the start of construction.
C. If
the schedule changes such that the dates and/or times on the ”No Parking” signs
needs to change, new “No Parking” signs will be installed with the correct
dates and/or times.
D. The Contractor shall allow for residential
parking on at least one side of the street at all times. ONLY
ONE (1) SIDE of the street shall be closed at any time for construction
of the valley gutters. The Contractor
shall finish installing and re-open the new valley gutters within seven (7)
calendar days after excavation.
E. During the street paving work, the
Contractor shall close the streets only during construction hours, but re-open
by the end of the workday. The duration
of the street paving work shall be further analyzed after the Contractor
submits a detail work schedule.
7. SITE
MAINTENANCE AND CLEANUP
Throughout
the construction period, the Contractor will maintain the job site for
cleanliness.
8. INSPECTION
All work will be inspected by the Public
Works Inspector, the Project Inspectors and their authorized
representatives.
9. SCOPE OF WORK
As part of Phase I, valley gutters on
both sides are proposed along Military Way El Camino Real to
10. CORRESPONDENCE
All written
correspondence or inquires should be directed to:
Murdo Nicolson, (murdo.nicolson@cityofpaloalto.org)
or
Public Works
Engineering
City of